Final Inspections were today... WE FAILED... but not for anything major... all easily fixable stuff!
Here are some pictures of each room on Dooms Day...
The list of things to take care of...
ELECTRIC
-GFI Outlets in basement
-Disconnect switch for well pump
-Remove laundry bar in laundry room
-3-way switch in attic steps
BUILDING
-Return handrails to basement
-Label radon in attic/basement
-caulk perimeter of basement for radon
-drywall under basement stairs
-block sliding door with railing
-caulk gas/vacuum pipe on exterior
-weather strip on attic door
FIRE
-smoke detector at base of basement stairs
PLUMBING
-vacuum breaks on hose bibs
-fasten dishwasher hose to high point
-caulk downstairs bathroom sink edge
-adjust shower temps
-cut out cabinet so you can see full outlet